Management’s view of Water-Related Projects:
Cost of Ownership
Item:
Cost without
EDI
Cost with EDI
(90 % Recycle)
UPW Operation
Savings
Electric Power
$6,200 + $1,800
$800 + $2723
$4,377
Chemicals (regen, cleaning)
$16,000
$1,600
$14,400
Pre-RO Filters
$16,000
$1,600
$14,400
Cost of water/discharge
$156,666
$15,666
$141,000
Misc. items (maintenance)
$3,000
$3,000
0
M&L to install 50 GPM EDI
$100,000
-$100,000
Totals
$199,666
$125,389
First Year, $74,277
Each year, $174,000
Totals with M&L upgrade
to 100 gpm
$399,332 (twice
the 50 gpm
costs)
$50,000 +
$125,789
First Year, $223,543
Each Year, $373,000